CDG Terminal 2E Reopening Date?  
User currently offlineRayChuang From United States of America, joined Jun 2000, 8016 posts, RR: 5
Posted (8 years 10 months 2 weeks 3 days 2 hours ago) and read 2497 times:

After watching History Channel's Modern Marvels program last night talking about the collapse of CDG Terminal 2E, one thing the program mentioned was the rebuilding of all of Terminal 2E, which we discussed here on Airliners.net back in March 2005.

Has Aeroport de Paris make an announcement on when will they finish the reconstruction? My guess is that they'll probably try to get it done in time for the arrival of the A380-800 in AF service, probably late 2007 to early 2008.

4 replies: All unread, jump to last
 
User currently offlineBoogyJay From France, joined May 2005, 490 posts, RR: 4
Reply 1, posted (8 years 10 months 2 weeks 3 days 2 hours ago) and read 2480 times:

You're right.

ADP (Aeroports de Paris) will destroy the Terminal (the part on the apron side, where the boarding waiting lounges are) and rebuild the vault.

Reopening is scheduled for the Winter 2007-2008.

As for the A380, I don't know if 2E has 80x80m gates, though I'd guess it has, as it's a quite new terminal (they must have thought about future growth). A new Terminal is being built especially for the A380 (5 gates?) at the end of T2, between 2E and 2F.


User currently offlineTaromA380 From Romania, joined Sep 2005, 334 posts, RR: 0
Reply 2, posted (8 years 10 months 2 weeks 3 days ago) and read 2413 times:

Why waiting so long for rebuilding the 2E ?

User currently offlineRayChuang From United States of America, joined Jun 2000, 8016 posts, RR: 5
Reply 3, posted (8 years 10 months 2 weeks 2 days 14 hours ago) and read 2288 times:

Quoting BoogyJay (Reply 1):
ADP (Aeroports de Paris) will destroy the Terminal (the part on the apron side, where the boarding waiting lounges are) and rebuild the vault.

Has ADP mentioned what kind of structure will replace the faulty arched roof design or shown drawings of what they will build?


User currently offlineBoogyJay From France, joined May 2005, 490 posts, RR: 4
Reply 4, posted (8 years 10 months 2 weeks 2 days 6 hours ago) and read 2230 times:

Quoting RayChuang (Reply 3):
Has ADP mentioned what kind of structure will replace the faulty arched roof design or shown drawings of what they will build?

I've found an article in English about that. Some key points:


  • The entire roof is to be demolished and rebuilt
  • They will keep the lower parts which are OK.
  • Re-opening in Winter '07-08.
  • "There was one single criterion: the safety of staff and passengers. Several so-called repair solutions were studied but we threw them out because they did not offer a total and unambiguous guarantee in the matter of safety"
  • That's the most expensive and longest solution (from a French article ).
  • Structural weaknesses caused the roof to collapse.
  • "the concrete suffered from "insufficient or badly positioned reinforcement," and that there was a lack of "redundancy" -- in other words the possibility of transferring stress to other parts of the structure."
  • An ADP spokesman Thursday denied suggestions that the two-and-a-half year delay before the original departure area is functioning again would effect the introduction of the Airbus A380 superjumbo, for which the terminal was conceived.
    "There is plenty of other space for the superjumbo at Charles de Gaulle," he said.


This last bit about the A380 is new to me. I didn't know that.

As for your question about the structure, it says that they will do studies. I'm not sure they will keep the same structure. I remember having read somewhere that they considered keeping the shape of the terminal but build the structure from metal instead of concrete, for it to be lighter. I don'tknow what the final solution is going to be.


Top Of Page
Forum Index

This topic is archived and can not be replied to any more.

Printer friendly format

Similar topics:More similar topics...
CDG Terminal 2E Question posted Wed Nov 1 2006 13:16:02 by AlitaliaMD11
CDG Terminal 2E To Be Demolished posted Thu Mar 17 2005 14:45:32 by Backfire
CDG Terminal 2E: Initial Inquiry Report posted Tue Jul 6 2004 13:44:59 by Geoffm
SFO-CDG Terminal 2E posted Tue Jun 29 2004 04:11:19 by Nantoine
All AF Flights To The US Now From Terminal 2E@CDG posted Thu Sep 7 2006 07:49:13 by Haggis79
Terminal 2E At CDG Reopened Partially Today posted Tue Aug 17 2004 20:34:52 by FLYSSC
CDG Terminal Evacuation posted Wed Oct 25 2006 21:50:39 by Trekster
Spotting Fra CDG Terminal 2? posted Mon Sep 18 2006 12:15:15 by Haavig
AF's Germany Flights Now In CDG Terminal 2F? posted Sat Jun 11 2005 17:56:04 by Sabena332
CDG Terminal 1 posted Mon Mar 14 2005 14:18:25 by TAP1972