What Are The Main Causes Of Airport Expansion?  
User currently offlinedelta88 From United States of America, joined May 2009, 86 posts, RR: 0
Posted (2 years 1 month 6 days 8 hours ago) and read 3240 times:
Support Airliners.net - become a First Class Member!

I know some answers might be obvoius, but im really wondering. What are the main causes of Airport Expansion, who says or who does what to get an airport to expand. I mean airport runway extensions, new Terminals, New Runways, and other things. Do the Airlines have a say, part or all?


707,717,727,738,744,752,762ER,763ER,772ER,MD82,MD-83,MD-88, DC-9-10,DC-10-10,A320
5 replies: All unread, jump to last
 
User currently offlineEK413 From Australia, joined Nov 2003, 4974 posts, RR: 4
Reply 1, posted (2 years 1 month 6 days 7 hours ago) and read 3168 times:

Quoting delta88 (Thread starter):

Well first of all the expansion of any major airport would come down to demand...

Let's use HKT as an example...

Current capacity 6.5 million passengers. The Airports of Thailand have approved works to commence on the expansion of the airport and apron due to the airport exceeding it's capacity capabilities of 6.5 which is to be doubled to 12 million... This has been approved due to the current infrastructure not capable of handling the current movements and to allow for growth in the tourism industry...

I have included a link...

http://www.skyscrapercity.com/showthread.php?t=1546271



Airports of Thailand (AoT) has begun work on Phuket International's THB5.7bn ($182m) expansion project. The contract has been awarded to Sino-Thai Engineering & Construction Public Company and is expected to be completed by April 2015.

The project will be performed in phases, with the first consisting of the construction of a new international terminal capable of handling six million passengers per year, which is expected to take one year to complete.

AoT said that following the completion of the new international terminal construction, work on modifications to the old terminal will commence.

According to the airport operator, completion of first phase of the project will expand the airport's handling capacity to 12.5 million international and domestic passengers every year, up from 6.5 million.

EK413



Good evening, ladies and gentlemen. We are tonight’s entertainment!
User currently offlineBeardown91737 From United States of America, joined Jun 2011, 558 posts, RR: 0
Reply 2, posted (2 years 1 month 6 days 7 hours ago) and read 3142 times:

Current usage is near or beyond the original planned capacity, gates are an issue, and usage is projected to keep growing. That was the situation at ONT in 1998.


135 hrs PIC (mostly PA-28) - not current. Landings at MDW, PIA, JAN.
User currently offlinedlramp4life From United States of America, joined Jun 2011, 947 posts, RR: 1
Reply 3, posted (2 years 1 month 5 days 15 hours ago) and read 2798 times:

Alot of growth has to do with airline and cargo growth. Most growth follows a master plan that the airport comission put together to forecast growth and what the airport needs and what needs to be done


PHX Ramp, hottest place on earth
User currently offlineViscount724 From Switzerland, joined Oct 2006, 25626 posts, RR: 22
Reply 4, posted (2 years 1 month 5 days 12 hours ago) and read 2769 times:

Quoting delta88 (Thread starter):
Do the Airlines have a say, part or all?

They certainly do where the airline and the airport have the same owner, such as EK and DXB (both owned by the government). Same for EY/AUH and QR/DOH.


User currently offlinePolot From United States of America, joined Jul 2011, 2257 posts, RR: 1
Reply 5, posted (2 years 1 month 4 days 18 hours ago) and read 2681 times:

Quoting delta88 (Thread starter):
Do the Airlines have a say, part or all?

All airports (or at least successful airports) consult with the airlines before undergoing expansion. They need to know how much more they are willing to pay in fees, along with gaining input on what works/what doesn't and how they should go about addressing airline's various issues. Although sometimes what the airlines (or certain airlines) want and what the airport (or certain other airlines) want are two completely different things.

No use in an airport building a new multi-billion dollar Taj Mahal terminal if it raises the airport's fees so much that airlines reduce flights negating its need in the first place.


Top Of Page
Forum Index

Reply To This Topic What Are The Main Causes Of Airport Expansion?
Username:
No username? Sign up now!
Password: 


Forgot Password? Be reminded.
Remember me on this computer (uses cookies)
  • Tech/Ops related posts only!
  • Not Tech/Ops related? Use the other forums
  • No adverts of any kind. This includes web pages.
  • No hostile language or criticizing of others.
  • Do not post copyright protected material.
  • Use relevant and describing topics.
  • Check if your post already been discussed.
  • Check your spelling!
  • DETAILED RULES
Add Images Add SmiliesPosting Help

Please check your spelling (press "Check Spelling" above)


Similar topics:More similar topics...
What Are The Rotation Speeds Of The TU-134 posted Mon Nov 18 2002 03:57:44 by Wardialer
What Are The Benefits Of Having A Prop Vs. A Jet? posted Thu Apr 12 2007 02:44:46 by UAL747
What Are The Small Bars On Top Of Doors? posted Tue Apr 18 2006 14:45:08 by Keta
What Is The Cabin Width Of An ERJ? posted Tue Jan 10 2012 17:39:04 by 747400sp
What Are The Rules For Record Locators? posted Tue Mar 29 2011 17:03:11 by Hagic
What Are The Two Black Spots? posted Thu Feb 24 2011 18:54:13 by jetbuff2011
What Are The Rules Regarding Contaminated Wings? posted Tue Dec 1 2009 20:20:06 by ACElite
Where Are The Six Pieces Of Wood In A 727? posted Thu Aug 28 2008 16:27:03 by Falstaff
Battery Powd Aircraft – What Are The Challenges? posted Sun Jul 6 2008 16:44:35 by GolfOscarDelta
What Are The Carts? posted Thu Aug 16 2007 05:00:47 by Flyabunch

Sponsor Message:
Printer friendly format