Quoting mjoelnir (Reply 9): You are talking about it being like a gift from Boeing and not a necessary expense to try to meet the conditions of the contract. |
Where? The charges are being incurred by Boeing at their expenses. The money does not go to the Air Force, the money is not requested by the Air Force, it is money that they are setting aside to get the program back on track. That's all there is to it. For some reason, you don't seem to be understanding this.
Quoting mjoelnir (Reply 9): So it seems to be very strange that the contract insist on test flights with the real K46 not only including demonstration of the refuelling capabilities.
Yes they are working at the birds, but they should be flying ,now according to the time plan. That is why somebody like the GAO is talking about delays. |
Where? Show me the contract wording insisting on this. The block tabulation is VH001 to VH004 which are listed as KC-46A / 767-2C. Not even the April GAO report states that it must be done on the KC-46A. It doesn't matter what test flights they do, they still count towards certification for either "variant" although they are one the same. The flutter tests for example are mostly being done with VH001 / EMD-1 which are not going to be repeated with VH002 / EMD-2 and etc etc. It's not necessary at all. EMD-3 will not be equipped with the refueling equipment as well which is still going to be treated as a KC-46A for certification purposes.
Quoting mjoelnir (Reply 9): That is why somebody like the GAO is talking about delays. |
And the GAO is also the one that pointed out the cost of the KC-45, your baby, would have cost the Department of Defense over $100 billion (2.5 a pop) in MILCON alone vs the cost of $40 billion (1 a pop). I'm quite aware of what the delays are which are pretty prominent. It's nothing to cry about which Boeing is incurring the cost which apparently you are disappointed about even though you're not a taxpayer? The GAO simply says that the AF should not go ahead with LRIP 1 until EMD-2 offloads fuel which isn't going to happen since Boeing already has committed the firing order which were sanctioned by the Air Force. Boeing does not add planes to the firing order until they are given confirmation by any customer regardless if it's military or civilian. Contract agreement w/ dates is not the same as the firing order.
Also in another GAO report from back in March of this year, it stated at the time of the report that more than 57% of the development work was completed and that Boeing met or exceeded all contractual requirements.
Now in that April report (that Leeham mostly skips over), which is omitted, in today's dollars the cost of the KC-46A acquisition on the Air Force's part, the cost went down from $51.7 billion (Feb 2011 dollars) to $48.9 billion (Dec 2014 dollars). The GAO stated that the program is ON TRACK to meet performance goals. With the flight hours, Leeham makes it sound like because there's no true KC-46A, flight hours will not be accumulated which is wrong. The contract agreement with the Air Force allows Boeing to use the two "baseline" 767-2C/KC-46A (EMD-1/EMD-3) and KC-46A (EMD-2) to fulfill all the 2400 flight hours necessary. EMD-1 has been flying for about 5 out of 7 days for the last 4 weeks with an average of about 2.5-3.5 hours which has been steadily growing upwards. Between now and end of 2015, that's easily 500 flight hours. Now back to the GAO report! What did Boeing and the Air Force plan to have at least how many flight hours? 400 which they want the total of 2400 flight hours. As EMD-2/EMD-3/EMD-4, it will start to tack up really fast. Now the reason why there's the 767-2C and KC-46A disparity is what Stitch pointed out, they need both the Amended Type Certificate (FAA) and military certificate (with all the refueling/avionics). Oh that 3.5 hours that Leeham was talking about? You know when that flight was? December 2014. Hi, we're in 2015, there's been many flight hours since then.
Now the GAO can only recommend to have the DoD make changes but ultimately the DoD has been making the final call which for the last 4 years, they've been mostly ignoring the GAO and going ahead with the KC-46A. In the same GAO report, it stated that they assume 18 will be delivered by August 2017 but the DoD expects 13 at least.
At the middle of the report, the GAO states this that Leeham left out!:
The program office projects that the KC-46 aircraft will meet all of its key performance goals,4 including receiving fuel from other tankers; providing fuel to about 36 receiver aircraft, according to an Air Force official’s projection; and having a certain amount of fuel to offload at various distances. According to program officials, the current assessment is based on their engineering expertise and the level of effort necessary to meet the requirements.
Now why did Leeham leave that out? Who knows! Maybe it sells page hits perhaps?
There's 7 categories that the GAO assessed Boeing on. They are:
Operational empty weight - Maximum weight of the aircraft without usable fuel.
Fuel usage rate assessment - Gallons of fuel per hour used by the aircraft during a mission.
Mission capable rate - Measure of how long the aircraft can perform one of its assigned missions.
Fix rate - The 12 hour fix rate for aircraft per 50,000 fleet hours.
Break rate - Number of breaks per sorties per 50,000 fleet hours.
Mission completion success probability - Probability of completing the aerial refueling mission and landing safely.
Operational availability - Probability an aircraft will be ready for operational use when required.
You know what the GAO rated them on in terms of "Projected to meet measure?" All 100% YES.
Quoting AngMoh (Reply 11): based on current progress there is no way that the first 7 will be delivered on time or even that the first delivery is by April 2016. |
Incorrect! There are already 4 right now as part of the first batch (the EMD). LRIP 1 will not start until the first quarter as planned which Boeing will be starting the next 3. So the timeline that they gave to the Air Force does work which it is entirely possible to get all 7 done.
Quoting AngMoh (Reply 11): Testing is just too far behind schedule and once the frames are up in the air, you will still see a slower than planned ramp up of test hours. |
Again incorrect. The charges are for the ramping up of flight hours. EMD-3 and EMD-4 will be going up soon to get the rate up faster. Historically and according to the GAO as well as the Department of Defense, the rate of flight tests is far more aggressive compared to other defense programs. The P-8, C-17, C-130J, C-27, C-5's have had far less than 30 flight hours per month vs the rate of 115 flight hours per month.
Quoting AngMoh (Reply 11): I just expect delays, cost overruns and the final tally to be far less than 179 frames. |
Do you understand when the contract is to be fulfilled by? 2028. The total cost of procurement is to be $31.6 billion for the remaining 175. They need to replace their KC-135's period which the Air Force wants to eliminate. KC-Y is going to be another round of the KC-46A and KC-Z is going to be a between the 787/777 (if Boeing puts that forward) and the A350/A330. So I seriously doubt the Air Force is going to kill the program to get less than 179 delivered. It seems to me that you are under the impression that Boeing must produce all 179 by end of decade or something?
Quoting AngMoh (Reply 11): And who knows how much delays the A330MRTT would have had with all USAF specific requirements... |
It wasn't going to be the A330MRTT. It was going to be built according to the USAF specification which is why the KC-45A was going to be an entirely different airplane (Airbus was supposed to deliver shell's to NG to work on) that the A330MRTT and why Northrop Grumman was the Prime Contractor until they withdrew from the bid. The Air Force begged NG to stay on but they knew they weren't going to win with the requirements as it is and they were caught by surprise when they "won" the first round.
Quoting mjoelnir (Reply 10): Karadion and now also you seem to think that the testing intended to do with the K46 is possible to do with the 767-2C. |
Because the plane is almost exactly the same on paper! After all it is the baseline for the KC-46A. There's very little difference between VH001 and VH002 other than the fact that Boeing left off the fueling and avionics equipment of VH001. They can simply add weight to make sure that the MEW matches close enough to that of a completed KC-46A. So the flight test are being certified as a KC-46A flight test with EMD-1 no matter how much you throw a fit about it.
[Edited 2015-08-19 21:24:32]