Moderators: richierich, ua900, PanAm_DC10, hOMSaR

 
User avatar
N328KF
Topic Author
Posts: 6130
Joined: Tue May 25, 2004 3:50 am

Re: Israeli Airforce Next Gen Helicopters Discussion Thread

Fri Dec 31, 2021 6:15 pm

Israel locked in 12 CH-53Ks (along with 2 KC-46s).

https://twitter.com/Israel_MOD/status/1 ... 6239388678
 
User avatar
kitplane01
Posts: 2917
Joined: Thu Jun 16, 2016 5:58 am

Israel's buy of CH-53K

Thu Jan 06, 2022 7:43 am

Israel is to buy 12 CH-53Ks. How does that work?

1) The Marines will give Israel some slots they had on the production line, delaying the Marine Corps own purchases?

2) LM will have a temporary rate increase to build these extra machines? Do they have the tooling/space/labor to have a temporary increase in production rate?

3) LM had some spare capacity in their production system? If so, had no one bought additional CH-53Ks would that have cost LM?

4) Something else??

https://news.usni.org/2022/01/05/israel ... elicopters
 
User avatar
SeamanBeaumont
Posts: 238
Joined: Sat Jun 05, 2021 3:12 am

Re: Israel's buy of CH-53K

Thu Jan 06, 2022 10:58 am

kitplane01 wrote:
Israel is to buy 12 CH-53Ks. How does that work?

1) The Marines will give Israel some slots they had on the production line, delaying the Marine Corps own purchases?

2) LM will have a temporary rate increase to build these extra machines? Do they have the tooling/space/labor to have a temporary increase in production rate?

3) LM had some spare capacity in their production system? If so, had no one bought additional CH-53Ks would that have cost LM?

4) Something else??

https://news.usni.org/2022/01/05/israel ... elicopters

Depends on the lead time required. If the Israelis are really pushy and need them asap then sometimes the US takes a side step. Usually from order to first delivery it is sometimes two and more often three plus years. In this case first CH-53K is scheduled for 2026 so Sikorsky has plenty of time to up the rate enough to slide the aircraft into the schedule, order the long lead parts yada yada.
 
GDB
Posts: 18172
Joined: Wed May 23, 2001 6:25 pm

Re: Israel's buy of CH-53K

Thu Jan 06, 2022 11:08 am

SeamanBeaumont wrote:
kitplane01 wrote:
Israel is to buy 12 CH-53Ks. How does that work?

1) The Marines will give Israel some slots they had on the production line, delaying the Marine Corps own purchases?

2) LM will have a temporary rate increase to build these extra machines? Do they have the tooling/space/labor to have a temporary increase in production rate?

3) LM had some spare capacity in their production system? If so, had no one bought additional CH-53Ks would that have cost LM?

4) Something else??

https://news.usni.org/2022/01/05/israel ... elicopters

Depends on the lead time required. If the Israelis are really pushy and need them asap then sometimes the US takes a side step. Usually from order to first delivery it is sometimes two and more often three plus years. In this case first CH-53K is scheduled for 2026 so Sikorsky has plenty of time to up the rate enough to slide the aircraft into the schedule, order the long lead parts yada yada.


2026? I know it was delayed but, if the source below is correct, after the IAF CH-53's they have leave service.
For all the it seems received wisdom of 'US helicopters always delivered on time, always work, Europeans ones, the opposite', while I agree that EADS, now Airbus Helicopters messed up with the NN-90, that was an all new design with work spread across multiple nations and services, what's Sikorsky's excuse?

https://en.wikipedia.org/wiki/Sikorsky_ ... g_Stallion

Shame because I always liked the CH-53 series.
 
User avatar
SeamanBeaumont
Posts: 238
Joined: Sat Jun 05, 2021 3:12 am

Re: Israel's buy of CH-53K

Thu Jan 06, 2022 11:17 am

GDB wrote:

2026? I know it was delayed but, if the source below is correct, after the IAF CH-53's they have leave service.
For all the it seems received wisdom of 'US helicopters always delivered on time, always work, Europeans ones, the opposite', while I agree that EADS, now Airbus Helicopters messed up with the NN-90, that was an all new design with work spread across multiple nations and services, what's Sikorsky's excuse?

https://en.wikipedia.org/wiki/Sikorsky_ ... g_Stallion

Shame because I always liked the CH-53 series.

2026 I grabbed from here, https://www.defensenews.com/air/2022/01 ... -53-helos/

The agreement includes an option for six more helicopters, the ministry said, adding that the first will arrive by 2026.


Extra stuff: Sorry just understood what you said. 2026 is the Israeli first delivery date, not the USMC timeline. The jarheads already have their first couple of frames.
 
User avatar
kitplane01
Posts: 2917
Joined: Thu Jun 16, 2016 5:58 am

Re: Israel's buy of CH-53K

Fri Jan 07, 2022 9:21 am

SeamanBeaumont wrote:
kitplane01 wrote:
Israel is to buy 12 CH-53Ks. How does that work?

1) The Marines will give Israel some slots they had on the production line, delaying the Marine Corps own purchases?

2) LM will have a temporary rate increase to build these extra machines? Do they have the tooling/space/labor to have a temporary increase in production rate?

3) LM had some spare capacity in their production system? If so, had no one bought additional CH-53Ks would that have cost LM?

4) Something else??

https://news.usni.org/2022/01/05/israel ... elicopters

Depends on the lead time required. If the Israelis are really pushy and need them asap then sometimes the US takes a side step. Usually from order to first delivery it is sometimes two and more often three plus years. In this case first CH-53K is scheduled for 2026 so Sikorsky has plenty of time to up the rate enough to slide the aircraft into the schedule, order the long lead parts yada yada.


I wonder how that works. I understand one can vary the labor force. But do they need to buy extra tooling and space to increase the rate, only to not need it after the Israeli order is done? It would seem inefficient to have the spare capacity just lying around, and the CH-53K was never going to attract lots of foreign orders like an F-16. It's not just capacity at LM, but also with all the suppliers of custom parts.
 
User avatar
SeamanBeaumont
Posts: 238
Joined: Sat Jun 05, 2021 3:12 am

Re: Israel's buy of CH-53K

Fri Jan 07, 2022 10:35 am

kitplane01 wrote:
SeamanBeaumont wrote:
kitplane01 wrote:
Israel is to buy 12 CH-53Ks. How does that work?

1) The Marines will give Israel some slots they had on the production line, delaying the Marine Corps own purchases?

2) LM will have a temporary rate increase to build these extra machines? Do they have the tooling/space/labor to have a temporary increase in production rate?

3) LM had some spare capacity in their production system? If so, had no one bought additional CH-53Ks would that have cost LM?

4) Something else??

https://news.usni.org/2022/01/05/israel ... elicopters

Depends on the lead time required. If the Israelis are really pushy and need them asap then sometimes the US takes a side step. Usually from order to first delivery it is sometimes two and more often three plus years. In this case first CH-53K is scheduled for 2026 so Sikorsky has plenty of time to up the rate enough to slide the aircraft into the schedule, order the long lead parts yada yada.


I wonder how that works. I understand one can vary the labor force. But do they need to buy extra tooling and space to increase the rate, only to not need it after the Israeli order is done? It would seem inefficient to have the spare capacity just lying around, and the CH-53K was never going to attract lots of foreign orders like an F-16. It's not just capacity at LM, but also with all the suppliers of custom parts.

The jarheads want around 200 airframes so it is pretty straight forward to plan ahead and slot an extra Israeli 12 into the prod run. They don't get all 12 at once, probably have them delivered over a two or three year period so easy to either up the rate or slow the USMC rate a little. Standard stuff as Israeli and FMS deals happen all the time, the primes are very much used to it.
 
User avatar
bikerthai
Posts: 7769
Joined: Wed Apr 28, 2010 1:45 pm

Re: Israel's buy of CH-53K

Fri Jan 07, 2022 12:01 pm

SeamanBeaumont wrote:
it is pretty straight forward to plan ahead and slot an extra Israeli 12 into the prod run.


Concur. The US has in the past swapped position slots to support allies schedules. That is why I was curious why they did not allow Israel to accelerate the KC-46 delivery slots. Perhaps it was more of a political decision. But that's for the other thread.

bt

Who is online

Users browsing this forum: aumaverick and 48 guests

Popular Searches On Airliners.net

Top Photos of Last:   24 Hours  •  48 Hours  •  7 Days  •  30 Days  •  180 Days  •  365 Days  •  All Time

Military Aircraft Every type from fighters to helicopters from air forces around the globe

Classic Airliners Props and jets from the good old days

Flight Decks Views from inside the cockpit

Aircraft Cabins Passenger cabin shots showing seat arrangements as well as cargo aircraft interior

Cargo Aircraft Pictures of great freighter aircraft

Government Aircraft Aircraft flying government officials

Helicopters Our large helicopter section. Both military and civil versions

Blimps / Airships Everything from the Goodyear blimp to the Zeppelin

Night Photos Beautiful shots taken while the sun is below the horizon

Accidents Accident, incident and crash related photos

Air to Air Photos taken by airborne photographers of airborne aircraft

Special Paint Schemes Aircraft painted in beautiful and original liveries

Airport Overviews Airport overviews from the air or ground

Tails and Winglets Tail and Winglet closeups with beautiful airline logos