Moderators: jsumali2, richierich, ua900, PanAm_DC10, hOMSaR
B777LRF wrote:If the “basic” A32xneo didn’t require a seperate TC, it’s hard to argue that what is effectively installing a larger centre-tank would do so.
The 10MAX is at risk it if fails to meet the 31DEC deadline, as all aircraft certified after that date must have (EI)CAS installed as standard. FAA is, in my opinion, likely to extend the deadline, but the question is whether the other big NAAs are going to follow suit.
The 777X is a strange kettle of fish. Looking back in history, discussing whether it should require a new TC would be largely pointless. Following the MAX scandal everything changed as we all know, and if anything this model may therefore carry the biggest risk. That would be a major setback, not only when it comes to a delayed EIS, but also because of the added certification costs and the loss of having a single 777 pilot pool. This may place some orders at risk, which in turn may jeopardise the financial viability of the program.
The Leeham article has some very interesting points at the end, regarding the current state of Boeing (and not just BCA). Not the best of times, to put it politely.
B777LRF wrote:If the “basic” A32xneo didn’t require a seperate TC, it’s hard to argue that what is effectively installing a larger centre-tank would do so.
The 10MAX is at risk it if fails to meet the 31DEC deadline, as all aircraft certified after that date must have (EI)CAS installed as standard. FAA is, in my opinion, likely to extend the deadline, but the question is whether the other big NAAs are going to follow suit.
The 777X is a strange kettle of fish. Looking back in history, discussing whether it should require a new TC would be largely pointless. Following the MAX scandal everything changed as we all know, and if anything this model may therefore carry the biggest risk. That would be a major setback, not only when it comes to a delayed EIS, but also because of the added certification costs and the loss of having a single 777 pilot pool. This may place some orders at risk, which in turn may jeopardise the financial viability of the program.
The Leeham article has some very interesting points at the end, regarding the current state of Boeing (and not just BCA). Not the best of times, to put it politely.
Opus99 wrote:I think when you look at Boeings problems in a list like that it’s kind of scary
planecane wrote:
The FAA became lax which led to the terrible MCAS design getting certified. Now the FAA has gone too far in the other direction and it is creating certification gridlock. The MAX 7 is just a shrink of the MAX 8 and it was used as the test bed for MAX 8 and MAX 9 recertification but it still isn't certified several months after the package was submitted to the FAA.
This doesn't just hurt Boeing as the other manufacturers will go through the same delays.
planecane wrote:The EICAS deadline is a deadline imposed by a law passed by the US congress and signed into law. The FAA can't extend the deadline, only congress can. The other NAAs do not have the same deadline.
.
zeke wrote:planecane wrote:
The FAA became lax which led to the terrible MCAS design getting certified. Now the FAA has gone too far in the other direction and it is creating certification gridlock. The MAX 7 is just a shrink of the MAX 8 and it was used as the test bed for MAX 8 and MAX 9 recertification but it still isn't certified several months after the package was submitted to the FAA.
This doesn't just hurt Boeing as the other manufacturers will go through the same delays.
I have very little sympathy for Boeing here, it was their corporate culture that pushed their DERs to try and reduce the cost they provided to airlines saying the MAX was the same as the NG. If they were not hell bent on this point, they would not have the problems they are having now. This is the bed they made, it is not the rank and file engineers and technicians that caused this, it is Boeing management.
planecane wrote:Boeing suffered major consequences due to the culture and bad decisions. I don't think they should continue to be punished for bad decisions made 10 years ago or more recent decisions made by people who are no longer at Boeing. There is no doubt that the FAA needed to have more direct oversight for aircraft certification so that something similar to the MCAS situation doesn't happen again.
planecane wrote:I also disagree that the rank and file engineers should not be blamed. The engineering of the MCAS system was incompetent. It doesn't matter what pressure management applied or what deadlines were imposed. As an engineer you just can't put out such an unsafe design. The failure scenario wasn't some kind of swiss cheese model that was difficult to predict with a fault tree. It was the simplest and most obvious failure mode.
zeke wrote:planecane wrote:I also disagree that the rank and file engineers should not be blamed. The engineering of the MCAS system was incompetent. It doesn't matter what pressure management applied or what deadlines were imposed. As an engineer you just can't put out such an unsafe design. The failure scenario wasn't some kind of swiss cheese model that was difficult to predict with a fault tree. It was the simplest and most obvious failure mode.
It was not rank and file engineers that set the policy that no additional training will be required for the MAX, and it was not rank and file engineers that wanted to keep non redundant systems, these were top level management directions.
alancostello wrote:While some of these may not 'need' a new certificate in a technical sense (I feel like the A321XLR needing a new type certificate is a real stretch), maybe they're needed to restore and bolster public confidence in these processes and procedures?
planecane wrote:
The FAA became lax which led to the terrible MCAS design getting certified. Now the FAA has gone too far in the other direction and it is creating certification gridlock. The MAX 7 is just a shrink of the MAX 8 and it was used as the test bed for MAX 8 and MAX 9 recertification but it still isn't certified several months after the package was submitted to the FAA.
This doesn't just hurt Boeing as the other manufacturers will go through the same delays.
planecane wrote:Boeing suffered major consequences due to the culture and bad decisions. I don't think they should continue to be punished for bad decisions made 10 years ago or more recent decisions made by people who are no longer at Boeing. There is no doubt that the FAA needed to have more direct oversight for aircraft certification so that something similar to the MCAS situation doesn't happen again.
Vicenza wrote:But yet it was due to the intense, and expensive, lobbying by Boeing itself which led to the FAA having major responsibilities removed from it, in order that Boeing could continue to hide it's bad safety/management culture and cost cutting practices. The same US Congress that then implemented the new laws, which Boeing (and the likes of yourself) still does not want to comply with by looking for more waivers/extensions.
JayinKitsap wrote:The SkyCourier is a clean sheet and a very basic airplane for the 9 and 19 seat category, it still took months and months longer than Cessna expected.
If the A321XLR does require a clean sheet certification while the A321LR didn't just a bit earlier it basically means that grandfathering is effectively dead. As so much is being digitally modeled to confirm the design, it appears the FAA & EASA wants an accurate digital model going forward for certifications, no longer references back to earlier certifications dating from when slide rules were used for the design.
Not mentioned was the new cockpit requirements that was part of the reason the MOM went quiet, are these revised regulations out, what is the standard for this new cockpit. There may be a silver lining here in that the 'new' cockpit is basically ready to be single pilot or autonomous except for the need for instrument observers for when the automation needs to be rebooted.
VV wrote:Do you think all potential derivative aircraft would be impacted?