Moderators: jsumali2, richierich, ua900, PanAm_DC10, hOMSaR
Quoting Ikramerica (Reply 1): As for Dec 15th being part of any schedule, that's the laugher. That date has been pushed back so many times, who the hell knows if it was picked out of a hat or a date that actually means something inside Airbus at this point. Considering delivery is nearly a year away, I'm not sure why Dec 15th really matters at all. |
Quoting OldAeroGuy (Thread starter): Certification testing still being done includes cross winds, autolands and of course route proving. My own experience says that if this level of testing is going on only a month before planned certification, it's unlikely that you're going to make the certification date. |
Quoting Ikramerica (Reply 1): Considering delivery is nearly a year away, I'm not sure why Dec 15th really matters at all. |
Quoting Stitch (Reply 8): This is just the "general" type certificate, correct? With the "manufacturer" configuration. Once they receive that, then they start on SQ's type certificate, followed by EK's and then QF's and then all the rest, correct? |
Quoting Dynkrisolo (Reply 6): Route proving might not need to be completed for the type certificate. |
Quoting OldAeroGuy (Thread starter): If the certification does slip into 2007, does it really matter? (Aside from an Airbus sense of accomplishment.) |
Quoting Poitin (Reply 5): What ever happen to the wing test? As it signed off on or not? I don't remember seeing anything about that for months. |
Quoting Jacobin777 (Reply 11): It was a nonevent, as Airbus was able to show to the authorities via their FEM's that adding some extra stringers, fasteners, etc would solve that problem..... |
Quoting WINGS (Reply 4): Well with this situation, the date has not been picked out of a hat. I you had read closely the FI report you would come across the following information. |
Quoting Osiris30 (Reply 10): Type, probably yes. Production, no. |
Quoting Ikramerica (Reply 14): my point was that if it REALLY mattered to Airbus, they would make people stay until Dec 16th, or 17th, etc, not let them take an extra week of vacation. |
Quoting Ikramerica (Reply 14): That makes sense, but my point was that if it REALLY mattered to Airbus, they would make people stay until Dec 16th, or 17th, etc., not let them take an extra week of vacation. I've never seen a company with such troubles operate with a complete lack of urgency. I think it shows a structural deficiency in the corporation. But beyond that, only a few weeks ago they were still talking about November certification... |
Quoting Poitin (Reply 12): Thank you, I figured as much |
Quoting EbbUK (Reply 17): What exactly happens at Certification? Apart from legal clearance to fly the plane, Does the weight of the plane become public knowledge? Does any other information come to light that will help for more accurate calculations about the certified plane's performance figures? |
Quoting Ikramerica (Reply 14): That makes sense, but my point was that if it REALLY mattered to Airbus, they would make people stay until Dec 16th, or 17th, etc., not let them take an extra week of vacation. |
Quoting Slz396 (Reply 15): Certification is done not by Airbus, but by EASA, a European government institution. The end of year is a public holiday period in Europe and even if Airbus would keep on working as normal, all government institutions are closed then. Since you can't just call civil servants in to work during public holidays, not even to certify the A380, it is either Dec 25th at the very latest or next year... |
Quoting RIXrat (Reply 20): If an when the A380 travels to the U.S., will the FAA also have confirm its airworthiness. As far as EASA is concerned a British parliamentary report had some scathing words for it in a just released report, calling it "half-baked" and "an accident waiting to happen." |
Quoting OldAeroGuy (Reply 19): |
Quoting OldAeroGuy (Reply 19): The MZFW, MTOW MLW MEW, |
Quoting EbbUK (Reply 23): maximun zero fuel weight? maximum take off weight, maximum load weight? maximum empty weight? |
Quoting OldAeroGuy (Reply 24): |
Quoting Pygmalion (Reply 25): |
Quoting Pygmalion (Reply 22): The FAA accepts a EASA TC (vice versa also) There are a few rules that are different but not many and those are usually handled on the side. |
Quoting WINGS (Reply 4): According to sources close to the process, EASA is working towards Friday 15 December for the approval. European industry closes for the entire week starting 25 December for the Christian religious festival of Christmas and do not return until 2 January 2007. Many workers also take the week commencing 18 December as additional vacation, making 15 December effectively one of the last working days in 2006. |
Quoting OldAeroGuy (Reply 24): The last is the most interesting since if this were to be known, it would provide the answer to the A380 overweight question. |
Quoting Slz396 (Reply 15): Certification is done not by Airbus, but by EASA, a European government institution. The end of year is a public holiday period in Europe and even if Airbus would keep on working as normal, all government institutions are closed then. |
Quoting WINGS (Reply 16): I agree with you 100% in regards to Airbus inability to make the deadlines with the A380 program. It indeed has become pathetic to be more accurate. Lets just see if they actually make it this time. |
Quoting Atmx2000 (Reply 28): Off topic, but why does a Western aviation magazine based in the UK have to refer to Christmas as a Christian religous festival? |
Quoting Pygmalion (Reply 25): OEW + PAX + Baggage+ Cargo = MZFW MZFW + Fuel = MTOW OEW is fixed (weight of the basic airplane). MTOW is a fixed structural and power limit. All others are variables. But when you add them all up to get MTOW, they have to be less than MTOW. So, if maximum fuel and maximum payload is higher than MTOW then something has to come off either limiting your payload or your range. |
Quoting OldAeroGuy (Reply 27): It's not quite this simple |
Quoting OldAeroGuy (Thread starter): What do others on the forum think? |
Quoting Dougloid (Reply 31): Zero fuel weight (ZFW) is not a variable. That's fixed, and it's the maximum amount the aircraft and its payload can weigh without fuel. The balance, up to maximum takeoff weight (MTOW) can be disposed of by loading as much fuel as you can handle without going over, but NOT more payload other than fuel. |
Quoting C133 (Reply 34): Actually, zero fuel weight IS a variable--MAX zero fuel weight is a limiting fixed number. On any given flight, payload items added to operating weight can be any number up to, but not exceeding, MZFW. Then fuel (a variable amount) can be added to this, up to, but not exceeding, MTOW and/or runway limited weight for the conditions. |
Quoting Pygmalion (Reply 32): You are exactly correct and I should have simplified it a lot less... It was late on a Friday and I wanted to get work done and go home. Good explanation btw. I thought it was a bit off topic and I simplified it too much, So thanks for the great explanation. |